Water and wastewater · Pump service contractor, West Sussex
Three Telemetrix panels for West Sussex County Council's landfill pumping stations
The contractor look after the pumping infrastructure at West Sussex County Council's landfill sites under a long-term asset management contract. They fitted three wastewater high-level Telemetrix panels so the council gets live status and alerts, and maintenance can be preventative rather than reactive.
- Customer
- Pump service contractor
- End client
- West Sussex County Council
- Panels
- 3 x Telemetrix, high level
- Sites
- Landfill pumping stations
The challenge
Closed landfill pumping stations visited on a schedule rather than daily, for a client that wants problems caught before they become spills.
What we supplied
Three Telemetrix wastewater panels, the same specification at each station, with the high level alarm and remote monitoring built in.
The result
Live status and alerts on all three stations, feeding preventative maintenance for the council.
The requirement
Reliable pumping at closed landfill sites that are visited on a schedule, not daily, for a public sector client that wants problems caught before they become spills. The panels had to give the contractor and the council warning of a high level or a pump trip without an ongoing monitoring subscription.
The constraints
- Remote sites: nobody on hand to notice a beacon, so the alert has to reach a phone.
- A public sector client under a long-term asset management strategy: documented, repeatable panels rather than one-offs.
- Three stations to install and commission alongside the week's routine work.
What we built
Three Telemetrix wastewater panels from the standard range, each with the high level alarm and remote monitoring built in: pump trip, high level and panel offline alerts by email and text to the contractor's team, connected over 4G or the site network. Same panel at each station, so the engineers and the council's records see one thing three times.
Delivery
Supplied from the Telemetrix range and installed and commissioned by the contractor's engineers within the week, alongside the induction of a new pump engineer on his first project.
The outcome
Real-time monitoring and alerts on all three stations, feeding the contractor's preventative maintenance for the council. In the contractor's words, the installation helps ensure "reliable waste management, sustainability and continued operational resilience" for the council's landfill sites.
Got a similar job?
Send the spec, points list or drawing and we will tell you what we would build, the price and the date.
“The detail, and thought that goes into making these installer and end user friendly is second to none. The best control panels we've seen, let alone had the pleasure of using. Great products.”
- Wiring diagram, test certificate and 12-month warranty with every panel
- Built to BS EN 61439-2 and BS EN 60204-1 in Stoke-on-Trent
- We reply during working hours, usually the same working day
More case studies

Butlins Skegness
One motor control centre for 64 motors in a water park plant room
The pool and water park plant room at Butlins Skegness needed a new motor control centre to run every pump, blower and feature from one place, with a BMS interface for the integrator's controllers. We designed and built it in Stoke-on-Trent.
Read the case study
Confidential London project
Every BMS control panel for a prestigious London building, from one supplier
The full BMS control panel supply package for a high-profile London building: every outstation and motor control panel across its plant rooms, designed, built and tested in Stoke-on-Trent and delivered to the contractor's programme. The client and project cannot be named.
Read the case study
SSE Energy Solutions
A Form 2 outdoor BMS panel on the roof in 12 working days
SSE Energy Solutions were refitting the third floor of Highgate Mental Health Hospital in London: new walls, heating, HVAC, electrical and controls throughout, with a new BMS tying into the trust's existing Trend network. The panel for it had to sit on the roof, and the only crane was coming down in three weeks.
Read the case studyGot a project, or just need a quick answer?
Tell us what the panel has to do and we will come back with a price and a lead time. Existing accounts: reorders and spares go through the same form.