Bulk tank selection and isolation valve panels, repeated depot by depot
A fuel storage and dispensing systems integrator needed a panel to control the selection and isolation valves between a depot's bulk tanks and its loading pumps. We designed the first in 2024 from their control philosophy, and have built it four more times since.
- Customer
- Fuel systems integrator
- Panels
- Valve selection and isolation
- Built
- 5 between 2024 and 2025
- Control
- Schneider PLC, UPS backup
The challenge
Let a fuel depot choose which bulk tank feeds its loading pumps, with the valves interlocked so a tank cannot be switched with a line open.
What we supplied
A PLC valve selection and isolation panel with limit switch feedback, traffic light outputs, an emergency stop that closes every valve and battery backup to drive them.
The result
Five panels in eighteen months as the integrator rolled the design out to more depots, each a repeat with the changes that site needed.
The requirement
Loading pumps at a fuel depot are fed from bulk tanks through three-port selection valves, which choose the tank, and two-port isolation valves. The integrator's control philosophy asked for a panel to drive them all: a tank selection can only change with every isolation valve closed, limit switch feedback lights the door and the site's traffic lights, and volt-free permissives inhibit the depot's existing pump panel.
The constraints
- The interlocks are the point of the panel: no selection change with any isolation valve open, with every valve position confirmed by its limit switches.
- The valves are in the depot's hazardous area. An ATEX version of the valve actuator the integrator wanted was proving hard to get, so closing the valves on a mains failure had to come from the panel.
- An emergency stop, with connections for remote stops, that closes every valve.
- A scope that grew during design, from four products to five.
What we built
A steel panel built around a Schneider PLC: the integrator was open to a basic PLC for the flexibility, and chose the Schneider controller over the Siemens LOGO! we had offered. The door is laid out in plates, one per valve, with closed and open lamps and a close/open switch, plus bulk tank select switches and power on, emergency stop active and battery fault lamps. A DIN-rail UPS with battery backup keeps the controls and valve supplies up long enough to drive the valves closed if the mains fails. Limit switch inputs, traffic light outputs and volt-free permissives to the pump panel are all on labelled terminals.
Delivery
The first panel was ordered in May 2024 and despatched at the end of July. The second followed in August with one change, a mains loss input to the PLC: in the integrator's words, "I need to place an order for another one of these panel please, with just one modification." A third went in October 2024, a fourth in September 2025, and a fifth in November 2025, simplified to five isolation valves with no tank selection for a depot that needed only that.
The outcome
One design, drawn once and adapted per depot, that the integrator orders when the next site comes up. Each one leaves Stoke-on-Trent with its own drawing and test certificate.
Photos
Got a similar job?
Send the spec, points list or drawing and we will tell you what we would build, the price and the date.
“The detail, and thought that goes into making these installer and end user friendly is second to none. The best control panels we've seen, let alone had the pleasure of using. Great products.”
- Wiring diagram, test certificate and 12-month warranty with every panel
- Built to BS EN 61439 and BS EN 60204-1 in Stoke-on-Trent
- We reply during working hours, usually the same working day
More case studies

Butlins Skegness
One MCCP for 64 motors in a water park plant room
The pool and water park plant room at Butlins Skegness needed a new MCCP to run every pump, blower and feature from one place, with a BMS interface for the integrator's controllers. We designed and built it in Stoke-on-Trent.
Read the case study
Confidential London project
Every BMS control panel for a prestigious London building, from one supplier
The full BMS control panel supply package for a high-profile London building: every outstation and motor control panel across its plant rooms, designed, built and tested in Stoke-on-Trent and delivered to the contractor's programme. The client and project cannot be named.
Read the case study
SSE Energy Solutions
A Form 2 outdoor BMS panel on the roof in 12 working days
SSE Energy Solutions were refitting the third floor of Highgate Mental Health Hospital in London: new walls, heating, HVAC, electrical and controls throughout, with a new BMS tying into the trust's existing Trend network. The panel for it had to sit on the roof, and the only crane was coming down in three weeks.
Read the case studyGot a project, or just need a quick answer?
Tell us what the panel has to do and we will come back with a price and a lead time. Existing accounts: reorders and spares go through the same form.